Paladio Paladio
Published on · Costs

Plant and machinery: how the hourly cost is calculated and when renting makes more sense

Carlos Pérez (Comandos) Carlos Pérez (Comandos) CEO of Paladio
7 min read
Sepia engraving of a man in a frock coat and epaulettes holding a two-pan balance with outstretched arms, a bundle of invoices on one pan and a pile of gold coins on the other, in a town square with people watching from both sides

The hourly cost of a machine is what it costs to have it operating for one hour, all in: depreciation, maintenance, fuel, operator and whatever charges apply. It is the number that goes into the unit price of any item that uses machinery, and it is one of the calculations most often copied from a handbook without checking.

And it is also where a loss almost nobody measures hides: an idle machine keeps costing.

The three blocks of the hourly cost

Fixed charges

They exist whether the machine is operating or not.

Depreciation. The value the machine loses through use, spread over its useful-life hours. It is calculated on the purchase value minus the salvage value, divided by the total useful hours.

Investment. The cost of the capital tied up in the machine. It is real even though it never leaves the bank account: that money could be somewhere else.

Insurance. Annual premium divided by annual operating hours.

Storage and custody. Where applicable.

Maintenance. Preventive and corrective, estimated as a percentage of depreciation or from your own history.

Consumption charges

They only exist while the machine operates.

Fuel. Consumption per hour under working conditions, not the catalogue figure.

Lubricants and filters.

Wear parts. Tyres, tracks, blades, teeth. Calculated by their useful life in hours.

Operating charges

Operator, at real cost: wages plus social charges and benefits. It is the same multiplier that applies to any labour, and leaving it out understates the cost by 50 to 120 %.

Helpers, where the machine requires them.

The variable that decides everything

Hourly cost = (annual fixed charges ÷ effective hours per year)
            + consumption charges per hour
            + operating charges per hour

Effective hours per year are the most sensitive variable in the calculation and the one most often inflated.

A machine budgeted at 2,000 hours a year that operates 1,200 has an hourly cost 67 % higher than calculated, because the fixed charges are spread over fewer hours. And that difference shows up in no report: it shows up in the year’s result.

Effective hours are not available hours. Deduct maintenance, moves, waiting, weather and the days the machine was on site without working.

An example

Backhoe loader, illustrative figures in dollars.

Annual fixed charges

ItemCalculationAnnual
Depreciation(90,000 − 18,000) ÷ 8 years9,000
InvestmentAverage value × 12 %6,480
InsurancePremium2,700
Maintenance60 % of depreciation5,400
Total fixed, annual23,580

With 1,400 effective hours a year: 16.84 per hour.

Consumption and operating charges

ItemPer hour
Fuel, 14 l/h at 1.1015.40
Lubricants and filters2.30
Tyres3.20
Operator, real cost12.50
Subtotal33.40

Total hourly cost: 50.24

And the point of the example: if the machine operated 2,000 hours instead of 1,400, the fixed block would drop to 11.79 per hour and the total cost to 45.19. An 11 % difference that depends not on the machine but on how much you use it.

Buy or rent

The honest comparison is not rental rate against hourly cost. It is this:

FactorIn favour of buyingIn favour of renting
Annual utilisationHigh and sustainedLow or intermittent
SpecificityGeneral use across several sitesSpecific machine for one item
CapitalAvailable or financeableScarce, better spent on the works
MaintenanceYou have a workshop or the capacityYou do not want that operation
Obsolescence riskLowHigh
Continuity of workStable pipeline of projectsIrregular pipeline

The practical rule: below a certain annual utilisation, renting is cheaper even if the rate looks high, because rental does not charge you for the hours you do not use.

And the classic mistake: buying a machine on the strength of one project’s utilisation, and discovering in year two that no project needs it. The machine keeps depreciating, keeps being insured and keeps taking up space.

The blind spot in the comparison: almost nobody includes the cost of unavailability. An owned machine that breaks down leaves the site stopped until it is repaired. A rental usually includes a replacement. That risk has a value, and it rarely enters the calculation.

What to record on site

Four pieces of data, and none of them needs a system:

Effective operating hours per machine per day. This is what validates —or disproves— the annual-hours assumption in the calculation.

Idle hours, with their cause. Breakdown, no work front, no material, weather, no operator. Each cause is solved differently, and only the first one belongs to the machine.

Real fuel consumption. Against the theoretical figure. A sustained deviation points to a mechanical fault, misuse or diversion.

Maintenance carried out, with date and machine hours.

The second one is the most revealing. A machine idle for lack of a work front is not a machinery problem: it is a coordination problem, and it is being paid for as if it were machinery.

Frequently asked questions

How do I estimate annual hours for a new machine?
From the utilisation of a comparable machine in your own company, not from the catalogue. And conservatively: it is the assumption that punishes the calculation most if it turns out optimistic.
Does the hourly cost include moves between sites?
It is usually treated separately, as a mobilisation charge, because it does not depend on operating hours. What matters is that it lives somewhere and does not get lost.
What about a machine idle on site but available?
It keeps generating fixed charges. That is why idle hours with their cause are such a valuable record: they turn an invisible cost into a number you can attack.
Is it worth renting with an operator?
It usually simplifies things and shifts the risk of skilled staff availability. In exchange you pay a higher rate and have less control over the operation. For specialised equipment, it is almost always worth it.
How often should I recalculate my hourly costs?
At least yearly, and whenever fuel price, operator cost or your real utilisation change materially. A catalogue of hourly costs from three years ago does not describe your operation today.
ABOUT THE AUTHOR
Carlos Pérez (Comandos)
Carlos Pérez (Comandos)
CEO of Paladio

Founder and CEO of Paladio. He has spent more than 15 years building financial products that touch the lives of millions of people. He writes about what he sees on site: how progress is really measured and where the money leaks.

See all their articles →

The next folio fills itself. Start today.

Request a demo